With all the nutplates installed during the previous session, it’s now time to install/ rivet the Bottom Inboard and Outboard Wing Skins for the Left and Right Wings. To start, I have decided to start with the Right Wing. According to the plans, there are 675 rivets that need to be installed to complete the Bottom Skins installation. Since there are so many rivets to install, I decided not to publish a post every day regarding how many rivets that were set. Instead, I kept track of all the rivets installed, when, and the length of the session. I use this blog entry to encompass all the work sessions associate with the installation of the Bottom Wing Skins on the Right Wing. I will use the same “format” for completing the Left Wing.
Friday, November 2nd: 53 Rivets
Saturday, November 3rd: 94 Rivets
Sunday, November 4th: 69 Rivets
Monday, November 5th: 55 Rivets
Wednesday, November 7th: 8 Rivets
Thursday, November 8th: 7 Rivets
Friday, November 9th: 86 Rivets
Sunday, November 11th: 132 Rivets
Tuesday, November 13th: 52 Rivets
Wednesday, November 14th: 74 Rivets
Thursday, November 15th: 45 Rivets